Road treatment programme

Road treatment programme

Where we are working this week

Full details of road works taking place throughout the county can be found using our online Roadworks map.

Conventional Surfacing Programme

New Road, Coleshill (19/12/16 to 20/12/16) Daytime surfacing work and the reinstatement of road markings using a road closure between 07:00 & 19:00hrs.

Pothole Action Fund Programme

Post Meadow, Iver Heath (19/12/16) Daytime targeted patching work using an informal road closure & localised traffic management between 08:00 & 16:00.

Opendale Road, Burnham (20/12/16)Daytime targeted patching work using an informal road closure & localised traffic management between 08:00 & 16:00.

Surface Dressing Remedial Work

B416 Windsor Road, Gerrards Cross – between Hedgerley Lane & Pickeridge Wood (19/12/16 to 20/12/16) Daytime retexturing work using mobile Stop & Go traffic management between 09:30 & 15:30.

Burnham Road/Woodlands Hill/Ship Hill & Littleworth Road, Littleworth Common - between A355 & Wooburn Common Road (20/12/16 to 21/12/16)Daytime retexturing work using mobile Stop & Go traffic management between 09:30 & 15:30.

 

Scheme overview

Where: Countywide
When: April 2016 to March 2017
Status: In progress
Summary: Programme targeting roads in need of substantial treatment
Responsible for works: Transport for Buckinghamshire (TfB)
Contact: 01296 382416

About the project

TfB’s capital maintenance programme is in its sixth year after it was identified that substantial investment in Buckinghamshire’s roads was urgently required.

Since 2011 in excess of £75 million has been invested to improve, maintain, and prolong the life and condition of the Buckinghamshire road network and between April 2016 and March 2017 a further £12 million will be invested on the road network. The work identified to take place in 2016/17 forms part of a 4 year rolling programme with an additional £30 million to be invested on the road network between April 2017 and March 2020.

Roads chosen for treatment in 2016/17 are a combination of local roads chosen by local elected Members, under the guidance of Transport for Buckinghamshire and strategic roads shown by road condition survey data to require priority treatment. Each scheme will be treated following analysis of specific condition, ensuring that the right treatment options are targeted in the right locations.

In excess of 200 separate schemes will be undertaken in 2016/17 and work has already commenced. Notifications will be given to affected residents and businesses affected by any specific scheme in advance of works taking place. Please access the file below for a full list of carriageway surfacing schemes confirmed for treatment this year. 

Roads are given different treatments, dependent on their requirements. See ‘Road Surface Choices Guide’ on the left hand menu for details.

 